NPL Construction Company will be replacing some natural gas pipeline in our neighborhood, as part of a multi-year project to replace nearly 100 linear miles of pipe in the Denver metro area. They anticipate starting the following projects in March:
· East Bruce Randolph Avenue from Milwaukee to Steele streets (to be complete by the end of March)
· East 25th Avenue from Franklin to Gilpin streets (to be complete in May)
· Franklin Street from East 25th to East 24th avenues (to be complete in June)
· East 24th Avenue from Franklin to Gilpin streets (to be complete in July)
· Gilpin Street from East 24th to East 23rd avenues (to be complete in August)
Inclement weather may delay construction, and work may occur along side and adjacent streets.
NPL has a representative available 24 hours a day, seven days a week at 303-435-5321 to discuss any concerns or to answer any questions you may have about this work. Xcel Energy also is available at all times at 1-800-895-4999.
The general hours of construction for all projects are 8 a.m. to 3:30 p.m. Monday through Friday. Parking along these streets and on side streets may be limited and driveways may need to be blocked for short periods of time. We apologize in advance for any inconvenience this may cause.
If you would like to receive email updates about this project or have questions, comment or concerns, send them to infocolorado@xcelenergy.com.